Project Risk Analysis


[Up] [Top]

Documentation for package ‘PRA’ version 0.6.0

Help Pages

ac Actual Cost (AC).
building_project Mid-Rise Commercial Building Construction Project
contingency Contingency Calculation.
cor_matrix Generate Correlation Matrix from Random Samples.
cost_pdf Cost Probability Density.
cost_post_pdf Posterior Cost Probability Density.
cpi Cost Performance Index (CPI).
cv Cost Variance (CV).
eac Estimate at Completion (EAC).
etc Estimate to Complete (ETC).
ev Earned Value (EV).
fit_sigmoidal Fit a Sigmoidal Model to Data.
grandparent_dsm Risk-based 'Grandparent' Design Structure Matrix (DSM).
mcs Monte Carlo Simulation.
parent_dsm Resource-based 'Parent' Design Structure Matrix (DSM).
plot.dsm Plot a DSM heatmap.
plot_sigmoidal Plot a Fitted Sigmoidal Model.
pra_mcp_server Start a PRA MCP Server
pra_tools Create PRA Tool Definitions for LLM Agent
predict_sigmoidal Predict a Sigmoidal Function Using Fitted Model.
print.dsm Print a DSM object.
print.mcs Print method for Monte Carlo Simulation results.
print.pra_sigmoidal_fit Print method for Sigmoidal Model
print.smm Print method for SMM results.
prob_net Probabilistic Network of Project Risks.
prob_net_learn Perform Bayesian Learning on a Probabilistic Network of Project Risks.
prob_net_sim Perform Inference on a Probabilistic Network of Project Risks.
prob_net_update Update a Probabilistic Network of Project Risks.
pv Planned Value (PV).
risk_post_prob Posterior Risk Probability.
risk_prob Bayesian Inference for Risk Probability.
sensitivity Sensitivity Analysis.
smm Second Moment Method Analysis.
spi Schedule Performance Index (SPI).
sv Schedule Variance (SV).
tcpi To-Complete Performance Index (TCPI).
vac Variance at Completion (VAC).